1. Volume first, everything else after
Every concrete order starts as a volume, and every volume is length × width × depth with the units made to agree. The trap is that the depth is almost always given in inches or centimetres while the plan dimensions are in feet or metres, and a 4-inch slab entered as 4 feet is out by a factor of twelve.
Each dimension here carries its own unit dropdown, so a slab is entered as
20 ft × 10 ft × 4 in exactly as it is written on the drawing. Internally
everything converts to cubic metres and back out once at the end, using the exact
1 yd³ = 0.764554857984 m³ rather than the 0.7646 in most reference tables.
For anything outside a pour — rebar weight in pounds against kilograms, a plan drawn in millimetres, an area quoted in square yards — the unit converter carries the same exact factors and the same habit of converting once rather than at every step.
| Pour | Formula |
|---|---|
| Slab, driveway, patio | length × width × thickness |
| Footing or strip foundation | length × width × depth |
| Wall or stem wall | run × height × thickness |
| Round column or post hole | π × (diameter ÷ 2)² × height |
| Stairs (solid flight) | width × rise × run × n(n + 1) ÷ 2 |
The first three are the same rectangular prism under different labels — the calculator renames the fields rather than pretending they are different arithmetic. Use How many of these? for identical repeats: four footings or six columns are entered once and multiplied, which is both faster and harder to get wrong than adding four volumes by hand.
2. Stairs are not a wedge
A solid flight of stairs is the one shape people consistently underestimate. Its cross-section is
a staircase, not a triangle, so the volume is rise × run × n(n + 1) ÷ 2 times the
width — the triangular-number series, because step one is one rise deep, step two is two, and so
on.
That series grows faster than the step count. Five steps at 7 in rise, 11 in run and 3 ft wide is 0.89 yd³; ten identical steps is 3.27 yd³ — not double but 3.7 times as much, because 55 units of rise × run instead of 15. Estimating stairs by scaling up a shorter flight is how a short load turns into a second delivery.
3. Waste, and why the ordered volume is never the drawing
The drawing gives an exact volume and the site never does. Sub-grade is not perfectly level, so a nominally 4-inch slab averages a little deeper. Forms bow outwards under the weight of wet concrete. Some is left in the barrow, the chute and the pump line. 10% is the usual allowance and it is the default here; tight forms on a prepared base can take 5%, and a rough excavation or a hand-dug footing can want 15% or more.
The Before waste and Waste added tiles keep both numbers on screen, because they answer different questions — one is what the structure contains, the other is what to order. On the 20 × 10 ft slab at 4 in that is 2.469 yd³ in the forms and 2.716 yd³ to order.
Then round up again at the supplier. Ready-mix is batched and sold in whole or half yards, and a short load fee for the extra half yard is cheaper than a cold joint where the truck ran out mid-pour. Running out is the one estimating error you cannot fix afterwards.
4. Bags or ready-mix, and where the crossover is
Bag counts use the yield printed on the bag, never the bag weight. An 80 lb bag of pre-mixed concrete makes about 0.60 ft³, because water and compacted paste account for part of the finished volume:
| Bag | Yield | Bag | Yield |
|---|---|---|---|
| 40 lb | 0.30 ft³ | 20 kg | 0.0093 m³ |
| 50 lb | 0.375 ft³ | 25 kg | 0.0116 m³ |
| 60 lb | 0.45 ft³ | 30 kg | 0.014 m³ |
| 80 lb | 0.60 ft³ | 40 kg | 0.0186 m³ |
Counts are always rounded up, since two thirds of a bag is not a thing you can buy. That 20 × 10 ft slab needs 123 × 80 lb bags — 9,840 lb of material, close to five tons to carry, and a mixer running for most of a day. Past roughly 40 bags ready-mix is usually cheaper and always faster, and above about 1 yd³ it is the only realistic way to place a slab in one continuous pour.
With a price entered the Estimated cost tile multiplies your rate by the volume including waste — per cubic yard on imperial, per cubic metre on metric. It is the concrete only: delivery, short-load and out-of-hours surcharges, pump hire, formwork, reinforcement, labour and finishing are all extra, and on a small domestic pour they can exceed the concrete itself.
Labour is the line that most often dwarfs the material. If you are pricing your own time or a crew's, the hours calculator totals a week of clock-in and clock-out times with unpaid breaks taken off and overtime split out, which is the figure that belongs next to the cost above.
5. Mixing on site: nominal mixes and dry volume
For a hand or drum mix, the Mixing it yourself panel breaks the same volume into cement, sand, coarse aggregate and water at a nominal ratio:
| Mix | Cement : sand : aggregate | Strength | Typical use |
|---|---|---|---|
| M5 | 1 : 5 : 10 | 5 MPa / 725 psi | Blinding, non-structural fill |
| M7.5 | 1 : 4 : 8 | 7.5 MPa / 1,087 psi | Levelling course under footings |
| M10 | 1 : 3 : 6 | 10 MPa / 1,450 psi | Patio bases, kerb backing |
| M15 | 1 : 2 : 4 | 15 MPa / 2,175 psi | Paths, shed and garden slabs |
| M20 | 1 : 1.5 : 3 | 20 MPa / 2,900 psi | Domestic slabs, driveways, footings |
| M25 | 1 : 1 : 2 | 25 MPa / 3,625 psi | Suspended slabs, columns, beams |
Quantities are worked out on a dry volume of 1.54 × the wet volume. Sand and aggregate are full of voids that close up once cement paste and water fill them, so the dry ingredients always measure more than the finished pour — ignoring that factor is the classic reason a site mix comes up a third short. Cement is converted at its bulk density of 1,440 kg/m³ and reported both in 50 kg bags and in US 94 lb sacks, and water at a 0.50 water-cement ratio.
For 2.077 m³ of M20 that is roughly 837 kg of cement (17 × 50 kg or 20 × 94 lb), 0.87 m³ of sand, 1.74 m³ of aggregate and 419 litres of water. Add water sparingly: extra water makes concrete easier to place and measurably weaker, and a mix at w/c 0.65 can lose a third of the strength of the same mix at 0.45.
6. Concrete Calculator FAQs
How much concrete do I need for a 20 × 10 ft slab?
At 4 inches thick, 2.469 cubic yards in the forms and 2.716 cubic yards with the usual 10% waste allowance — so order 3. That is 2.077 m³, 73.33 ft³, or 123 bags of 80 lb pre-mix. Change the thickness and the figures follow immediately.
How do I calculate cubic yards of concrete?
Multiply length × width × thickness with all three in the same unit, then divide cubic feet by 27. Because the thickness is normally quoted in inches, the safer route is to let each dimension keep its own unit — 20 ft × 10 ft × 4 in — which is how the fields above work.
How many 80 lb bags of concrete are in a cubic yard?
45. A cubic yard is 27 ft³ and an 80 lb bag yields about 0.60 ft³. It is 60 bags of 60 lb, 72 of 50 lb and 90 of 40 lb. Bag counts are rounded up, since part of a bag is not something you can buy.
How much waste should I allow?
10% is the standard allowance and the default here — sub-grade is never perfectly flat, forms bulge, and some concrete stays in the barrow and the chute. Tight forms on a prepared base can take 5%; a rough excavation or hand-dug footing can want 15%. Then round up to the half yard your supplier batches in.
Is it cheaper to use bags or ready-mix?
Bags win on very small pours and lose quickly. Past roughly 40 bags — a little over a cubic yard — ready-mix is usually cheaper and always faster, and it is the only practical way to place a slab in one continuous pour rather than in cold-jointed batches.
What is the right mix ratio for a driveway?
M20, a nominal 1 : 1.5 : 3 of cement, sand and coarse aggregate, giving about 20 MPa or 2,900 psi. Paths and garden slabs are usually fine at M15 (1 : 2 : 4), while columns and beams call for M25 (1 : 1 : 2). Anything structural should follow a designed mix rather than a nominal one.
Why do the site-mix quantities add up to more than the pour?
Because dry volume is taken at 1.54 × the wet volume. Sand and aggregate contain voids that close up once cement paste and water fill them, so dry ingredients always measure more than the finished concrete. Skipping that factor is the usual reason a hand mix comes up short.
How much does concrete weigh?
About 2,400 kg per cubic metre, or roughly 4,050 lb per cubic yard, for normal-weight concrete — which is the figure the wet weight tile uses. Lightweight mixes run 1,800 to 2,000 kg/m³. It matters for skip loading, barrow runs and anything you are pouring on top of.
Does this tell me how thick my slab or footing should be?
No, and no volume calculator can. Slab thickness, footing width and depth, frost depth and reinforcement come from your local building code and the load the structure carries. This works out how much concrete a given size takes; it does not decide the size.